In early October, the Town of Oakville said construction hoarding and wayfinding signs were going up around Towne Square, and that the businesses on the square would stay open. The signs mark the start of a $7.5 million rebuild of the square, which has been a gathering place in downtown Oakville for more than 35 years. It sits at the intersection of Lakeshore Road and George Street.

The construction schedule was built around the holiday tree. The Town planned the first months of work so the square would be usable again by late November, then stop all construction until February. Most of the change to how the square is used comes after that, between February and September 2027.

A construction schedule built around one evening

In May 2026, council approved what Town staff called an "Optimal Phasing Plan" for the project. The staff report behind it says plainly what the winter break is for:

An over-winter pause (Stage 6, Nov 2026 – Feb 2027) ensures the square is fully operational for the holiday season, including the Christmas Tree Lighting Ceremony

According to the same report, the site stays "secured in temporary transition condition" through the four-month pause, and all tenants keep their access through the winter.

The evening it protects is Light Up The Night, which the Downtown Oakville BIA has scheduled at Towne Square for Friday, November 20, 2026, from 5 to 9 p.m. The BIA lists live music by The Ault Sisters, a visit from Santa, horse-drawn wagon rides, hot chocolate and holiday carollers. The tree lighting countdown starts at 6 p.m. Lakeshore Road East will be car-free between Thomas Street and Dunn Street for the evening. Full details are on the BIA's event page.

Oakville News reported in September that the BIA had confirmed the tree lighting would stay at Towne Square for the 2026 season.

The fall work was planned around the storefronts

The plan for this fall's work was narrow. Before crews reached the open plaza, the phasing report scheduled short stages along individual storefronts: new granular base, pavers, waterproofing and area drains along each business frontage. The work was to happen outside business hours, with lower-impact storefronts going first.

The May report named the businesses in order:

  1. Soontorn Bahn Thai and its neighbor's frontage, about 21 days
  2. 7Enoteca, on the east side, about 18 days
  3. Hexagon, on the south side, about 16 days
  4. Burrows Clothiers, at the northwest corner, about three days
  5. Towne Square Gallery, on the west side, about 11 days, including manhole coordination

The report's calendar started this sequence on September 2 and had it running to November 9. The Town later set the start for the week of September 14, so the dates printed beside each stage are best read as the planned order of work. The report also called its overall timeline a best case, because hidden conditions in the slab could add time.

Two other preparations were announced for before construction started. The Millennium Tower Clock was to be taken down and put in storage, and Town staff confirmed it will return once the project is finished. Work areas were to be enclosed with decorative hoarding, with signs showing the way to each business.

February is when the plaza itself closes

The storefront stages are the warm-up. The plan's seventh stage covers the central plaza, scheduled from February 9 to August 2, 2027, or about six months. Next summer, the open middle of the square, where people currently sit, cut through and gather, will be a work zone.

Stage Area Planned window What it means on the ground
7 Central square, main plaza Feb 9 – Aug 2, 2027 Four public entrances kept open; main construction entrance from Robinson Street
8 Leela Eco Spa frontage, south corridor Aug 3 – Aug 16, 2027 Modified operating hours planned for Leela Eco Spa
9 Brosko service entrance and parking elevator Aug 17 – Aug 23, 2027 Public and tenant parking elevator stays open 24/7
10 Paul Vincent Hair frontage, southwest corner Aug 24 – Sept 16, 2027 Brosko service entrance stays open 24/7

The street grid changes as well. Oakville News reported that George Street between Lakeshore Road East and Church Street will close from spring 2027 until construction ends in September, while the CIBC parking lot and Municipal Lot 3 stay accessible. Anyone who drives in on George Street to reach the Church Street lots will use a different route for most of next year.

The phasing plan also protects the elevator, the prep kitchen stairs and the entrance to the underground garage in every phase. Under the approved plan, construction staging and worker parking move off-site to keep traffic down in the downtown core, and extended work hours are used only when needed.

Where downtown's winter moves

With the tree lighting staying at Towne Square, the BIA's other winter events are moving west. Oakville News reported that the BIA plans to hold its winter events at Centennial Square, 120 Navy Street. For anyone walking from the east side of downtown, the center of the season's activity shifts a few blocks along Lakeshore toward Navy Street.

When the phased plan was approved, InsideHalton reported that it was designed to accommodate BIA events. The outlet also reported that BIA executive director Susan Johnston welcomed the phased approach, saying businesses would remain open and visible. For summer 2027, the Town told Oakville News that the George Street closure timing was meant to accommodate other downtown events and activities wherever possible.

Eight years from approval to the first hoarding

Part of the reason the schedule bends around the holidays is that it has already been rescheduled many times. Council approved the reconstruction in 2018. The pandemic paused it in 2020. A January 2026 start was then pushed back when council chose to avoid construction through summer 2026. The budget grew over that time as well. An October 2025 estimate put the project at $4.3 million, and the current figure is $7.5 million, with the scope of work also expanding through this year's revisions.

Downtown has been through this kind of work before, and the approach is different this time. The Lakeshore Road East reconstruction, from Navy Street to Allan Street, ran in two phases. Phase one, Navy to Dunn, started on April 22, 2019, and phase two, Dunn to Allan, began in January 2020. The Town marked the reopened road in 2020. That project moved block by block along the main street. The Towne Square plan goes storefront by storefront, then takes the plaza, then returns to the edges. Each stage is short, and the stages stop for the holidays.

The Town expects the full project to take eight to ten months of work, finishing in September 2027 if everything goes to plan. The finished square is planned to include:

  • Amphitheatre-style seating for community gatherings and events
  • A water feature, raised planters and seating areas
  • New trees, more landscaping and an updated central lawn
  • Decorative lighting and new accessible paving throughout

The Town said it will publish updates and construction milestones on its Towne Square Revitalization Project page. That page is the place to check before February 9, when the plaza stage is scheduled to begin.

Many of our clients live, walk and shop within a few blocks of Towne Square, and a year of planned construction downtown raises practical questions about timing, access and what the street will look like on the other side of it. If you would like to talk through how the downtown work fits into your own plans, Bernard Team would be glad to help. Schedule a consultation.

Three real estate agents review property materials together on a cream sofa. Three real estate agents review property materials together on a cream sofa.

About the Author - Bernard Team

The Bernard Team is dedicated to providing an unparalleled level of service, ensuring that our clients' needs are met with integrity, professionalism, and care.

We specialize as Oakville real estate agents, including the neighbourhoods of Old Oakville, Southeast Oakville, South Oakville, Southwest Oakville, Joshua Creek, Glen Abbey, and nearby areas.

Work With Us

As a leader in the residential real estate sector, we understand the importance of providing service at every level of today’s highly complex transactions. Our ability to interpret market information, balanced with strong intuition, will give you a leg up on the competition.

Follow Me on Instagram